Second-source qualification removed a single-supplier dependency
- Challenge
- A critical machined component was available from a single supplier whose lead time had extended from six to eighteen weeks, with no contractual protection against further slippage.
- Result
- A qualified second source was in place within four months, lead time on the component returned to eight weeks, and the original supplier improved terms once dependency was removed.
4 months
To qualified second source
18 → 8 wks
Lead time recovered