Shutdown-critical valve package delivered against a fixed turnaround window
- Challenge
- A planned turnaround required 68 process valves with full material traceability. The original supplier confirmed a lead time four weeks beyond the shutdown date, with no route to recovery.
- Result
- The complete package arrived eleven days before the turnaround with certification collated into a single data book. No valve was rejected at goods-in and no scope was deferred to the next shutdown.
68
Valves supplied
11 days
Ahead of shutdown