Lead time is designed in, not negotiated later
By the time a purchase order is raised, most of the lead time has already been fixed by the specification. Displacement, control type, shaft, ports and paint are decided by engineering, and only some of those decisions have any bearing on whether the pump works in the application.
Control type is usually the expensive choice
Standard pressure compensated controls are stocked. Electro-proportional controls with specific command characteristics frequently are not. Where the circuit genuinely needs closed-loop control, that cost is justified. Where it was specified because a previous machine used it, it is worth revisiting.
Shaft and port variants multiply quickly
A single displacement can exist in dozens of shaft and port permutations. Matching an existing installation is a legitimate reason to pick an unusual combination. Copying a model code from a decade-old drawing is not, particularly when the current-production equivalent is available from stock.
Ask what is already on the shelf
Before finalising the model code, ask the supplier which nearby variants are stocked. It is common to find that a functionally identical unit is available immediately while the specified one is a ten-week build, and that the difference is an adapter plate.
Document the reasoning
The most useful output of a specification review is a short record of why each non-standard choice was made. It means the next person to buy the part knows what is negotiable and what is not.